Summary
Western Area Power Administration (WAPA) and Beale Air Force Base (AFB), as joint lead agencies, prepared DOE/EA-2152 on the proposed interconnection of Beale AFB to WAPA's existing Cottonwood-Roseville 230-kilovolt (kV) line in Yuba County, California. The proposal includes a 5-mile, 230-kV/60-kV interconnection between WAPA's Cottonwood-Roseville transmission line and an existing substation on Beale AFB, and a new substation to be located on Beale AFB.
For more information, see https://www.wapa.gov/regions/SN/environment/Pages/Beale-WAPA-Interconnection-Project-BWIP.aspx.