DOE/EA-2141: Finding of No Significant Impact

Finding of no significant impact (March 6, 2021) for the Sterling Solar 2 Interconnection Project (DOE/EA-2141) in Arizona.

Office of NEPA Policy and Compliance

March 6, 2021
minute read time

EA-2141 Sterling Solar 2 Interconnection; Mohave County, Arizona

Based on Sterling Solar 2 Interconnection Project (DOE/EA-2141), Western Area Power Administration issued a finding of no significant impact for the proposed interconnection and project-related transmission system upgrades for the Sterling Solar 2, a proposed 225-megawatt photovoltaic generation facility on private land.

For more information, see Sterling Solar 2 Interconnection Project