CX-022016: Devils Lake Substation Expansion Stage 06

The project scope includes the following, expand the yard to the southeast for a new 115-kV area, replace transformer KY1 A and relocate, construc…

Office of NEPA Policy and Compliance

April 24, 2020
minute read time

The project scope includes the following, expand the yard to the southeast for a  new 115-kV area, replace transformer KY1 A and relocate, construct a  new control building, retire all the 115-kV equipment except for the cap banks, retire the 41.8-kV cap banks and associated interrupters.