Summary

The Western Area Power Administration (WAPA) is considering an interconnection to the existing Ault Substation. The proposed Project’s generation tie-in (gen-tie) line would interconnect with Western Area Power Administration’s (WAPA’s) adjacent Ault Substation. The approximately 0.2-mile-long 345-kilovolt (kV) gen-tie line would extend south from an on-site Project substation, across Weld County Road (CR) 86 to the existing Ault Substation.