EIS-0447: Final Environmental Impact Statement

Champlain Hudson Power Express Transmission Line Project, New York

Office of NEPA Policy and Compliance

August 8, 2014
minute read time

DOE prepared this Final EIS to evaluate the potential environmental impacts of a DOE proposal to grant a Presidential permit to Champlain Hudson Power Express, Inc., to construct, operate, maintain, and connect a new 1000-megawatt (MW) electric transmission system across the U.S.-Canada border near Champlain, New York, to New York City.