FONSI for the 12.6-mile long Avista Utilities 115-kV transmission line rebuild project on the Hanford Site
Office of NEPA Policy and Compliance
August 1, 2019Benton-Othello 115-kV Transmission Line Rebuild Project; Hanford Site, Washington
DOE prepared a finding of no significant impact for the proposed 12.6-mile long Avista Utilities 115-kV transmission line rebuild project on the Hanford Site.
For more information, see Benton-Othello 115-kV Transmission Line Rebuild Project.