DOE/EIS-0183: Record of Decision for Electrical Interconnection of the Kittitas Valley Wind Project (September 2009)

Electrical Interconnection of the Kittitas Valley Wind Project

Office of NEPA Policy and Compliance

September 4, 2009
minute read time

Electrical Interconnection of the Kittitas Valley Wind Project

The Bonneville Power Administration (BPA) has decided to offer contract terms for interconnection of up to 108 megawatts (MW) of power to be generated by the proposed Kittitas Valley Wind Project (Wind Project) into the Federal Columbia River Transmission System (FCRTS). Sagebrush Power Partners, LLC (Sagebrush) has received authorization from the Washington Energy Facility Site Evaluation Council (EFSEC) to construct and operate the proposed Wind Project in Kittitas County, Washington, and has requested interconnection to the FCRTS on BPA’s Columbia-Covington 230-kV transmission line in the vicinity of Ellensburg, Washington. BPA will construct a new substation to accommodate this additional power into the FCRTS.