Finding of No Significant Impact (DOE/EA-2093) for the Charlie Creek to Garrison Transmission Line Rebuild Project.
Office of NEPA Policy and Compliance
January 1, 2020Charlie Creek to Garrison Transmission Line Rebuild Project
Western Area Power Administration issued a Finding of No Significant Impact based on the EA for Charlie Creek to Garrison Transmission Line Rebuild Project (DOE/EA-2093), which assesses the potential environmental impacts of rebuilding 95 miles of the existing Charlie Creek to Garrison transmission line in Mercer, Dunn, and McKenzie Counties, North Dakota.
For more information, see Charlie Creek to Garrison Transmission Line Rebuild Project.