Final Environmental Assessment (DOE/EA-2050) for the Marys Peak BPA Communications Site.
Office of NEPA Policy and Compliance
December 15, 2021Marys Peak BPA Communications Site Project; Benton County, Oregon
Bonneville Power Administration (BPA), with the U.S. Forest Service and Bureau of Land Management as cooperating agencies, prepared final DOE/EA-2050, which evaluates the potential environmental impacts of alternatives for maintaining and upgrading the existing Marys Peak BPA Communications Site, part of the communications network that supports BPA’s power transmission system.
For more information, see Marys Peak BPA Communications Site Project.