DOE/EA-1589: Finding of No Significant Impact

FONSI for replacing 4 miles of unlined canal with underground pipeline and relocating up to 40 transmission structures.

Office of NEPA Policy and Compliance

June 1, 2007
minute read time

Contra Costa Canal Replacement Project; Contra Costa County, California

Based on DOE/EA-1589 [insert project page URL], prepared by the Bureau of Reclamation (BOR) with DOE’s Western Area Power Administration (WAPA) as a cooperating agency, WAPA issued a finding of no significant impact for a proposal to replace the unlined portion (3.97 miles) of the Contra Costa Canal, a BOR-owned facility, with a buried pipeline within BOR’s existing right-of-way (ROW). WAPA would relocate up to 40 structures of its existing Tracy-Contra Costa 69-kV transmission line; the new structures would be within the existing transmission line ROW.

For more information, see Contra Costa Canal Replacement Project.