CX-102055: Integrated Development and Comprehensive IO&M Testing at RITE of a KHPS TriFrame Mount

Award Number: DE-EE0007349, CX(s) Applied: A9, B5.25, Water Power Technologies Office, Location(s): NY, Office(s): Golden Field Office

Office of NEPA Policy and Compliance

February 18, 2021
minute read time

Award Number: DE-EE0007349
CX(s) Applied: A9, B5.25
Water Power Technologies Office
Location(s): OR
Office(s): Golden Field Office

The U.S. Department of Energy (DOE) is proposing to provide federal funding to Verdant Power, Inc. (Verdant) to conduct an integrated design process to develop, build, deploy and operate a TriFrame mounting structure with three Verdant Power Gen5 KHPS tidal water turbines at the Federal Energy Regulatory Commission (FERC) licensed Roosevelt Island Tidal Energy (RITE) Project in the East River of New York City, NY.