CX-029717: Grand Coulee - Foster Creek - 1 Impairment Project

Bonneville Power Administration (BPA) proposes to correct five impairments on the Grand Coulee - Foster Creek - 1 transmission line. An impairment …

Office of NEPA Policy and Compliance

January 2, 2024
minute read time

Bonneville Power Administration (BPA) proposes to correct five impairments on the Grand Coulee - Foster Creek - 1 transmission line. An impairment is an area where the distance from the conductor to the ground surface is inadequate, per National Electrical Safety Code (NESC) standards, resulting in a threat to line reliability and posing a risk to public health and safety.