The Western Area Power Administration (WAPA) is proposing to replace insulators at Structures 92/1 - 92/3 on the Glen Canyon (GC) - Flagstaff (FLG)…

Office of NEPA Policy and Compliance

July 10, 2019
minute read time

The Western Area Power Administration (WAPA) is proposing to replace insulators at Structures 92/1 - 92/3 on the Glen Canyon (GC) - Flagstaff (FLG) #1 transmission line segment. Work would be accomplished using crew trucks and bucket trucks. Existing access roads would be used to get to/from the project area. There would be no ground disturbance. The project would begin July 8, 2019 and end on July 12, 2019.