Categorical Exclusion Determination
Office of NEPA Policy and Compliance
July 30, 2018Contractor shall provide all labor, tools, equipment, materials, consumables, services, transportation, storage and supervision necessary to replace the foam deluge piping. This work includes demolishing approximately 6,500 feet of foam deluge piping and replacing it with carbon steel piping. It also include the demolition of three hose reel headers and a flanged 8-inch spool.