CX-017171: Property and Easement Acquisition, Flathead-Hot Springs and Kalispell-Kerr Transmission Lines

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

November 20, 2017
minute read time

Bonneville Power Administration (BPA) proposes to purchase one tax lot, 5 acres in size, and a transmission line easement from two private landowners. Purchasing the tax lot and easement will ensure BPA can access its existing Kalispell-Kerr 115 kilovolt (kV) transmission line and Flathead-Hot Springs 230 kV transmission line transmission structures, and operate and maintain the lines in the future. BPA would not acquire any groundwater or mineral rights. 

CX-017171.pdf (308.53 KB)