Electrical Isolation of 652-68G and 652-70G TransformersCX(s) Applied: B4.10Date: 09/09/2009Location(s): Aiken, South CarolinaOffice(s): Environmental Management, Savannah River Operations Office
Office of NEPA Policy and Compliance
September 9, 2009CX(s) Applied: B4.10
Date: 09/09/2009
Location(s): Aiken, South Carolina
Office(s): Environmental Management, Savannah River Operations Office
Substations 652-68G and 652-70G will be deenergized and isolated by cutting and grouting the conduit from the site electrical grid.