CX-028085: Longhorn Substation Construction and McNary-Coyote Springs No.1 Line Modifications (Update to Previous CX issued April 26, 2023)

Bonneville Power Administration (BPA) proposes to construct a new 500/230-kilovolt (kV) Longhorn Substation, which would also require some modifica…

Office of NEPA Policy and Compliance

May 31, 2023
minute read time

Bonneville Power Administration (BPA) proposes to construct a new 500/230-kilovolt (kV) Longhorn Substation, which would also require some modifications and upgrades (i.e., replacing structures, raising structures to remediate impaired spans, and relocating portions of an existing fiber optic cable onto new wood poles) along the existing 500-kV McNary-Coyote Springs No. 1 transmission line in Morrow and Umatilla counties, Oregon.