Categorical Exclusion Determination
Office of NEPA Policy and Compliance
September 28, 2018Bonneville Power Administration proposes to add equipment at the Central Ferry Substation to accommodate load growth and prevent transformer overloading due to inadvertent flow. The new electrical equipment to be installed is a spare 230/500-kilovolt transformer. The new substation equipment would be installed on concrete pads for stability.