CX-016878: Noxon-Libby No. 1 Span 14/4, 14/5, 17/4, and 21/1 Impairment Remedy

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

September 25, 2017
minute read time

Bonneville Power Administration proposes to decommission existing septic tanks and drainfields at Covington Substation. Bonneville Power Administration would replace this septic system with a new sanitary sewer system. The new sewer system would accommodate all sewage from existing facilities at Covington Substation and future maintenance headquarters facilities. 

CX-016878.pdf (88.04 KB)