Audit Report: IG-0598

Status of the National Ignition Facility Project

Office of Inspector General

April 29, 2003
minute read time

April 28, 2003

Status of the National Ignition Facility Project

Construction of the National Ignition Facility, a 192-beamline 1.8 megajoule laser being built by Lawrence Livermore National Laboratory (Livermore), began in 1997. The project is comprised of six major components: conventional facility; laser system; target experimental system; integrated computers and controls; assembly, installation, and refurbishment equipment; and utilities. To manage the project to the revised schedule and cost baselines, Livermore established control account plans for each of the six components in conjunction with a work breakdown schedule. Control account managers were assigned and held responsible for maintaining the schedule and keeping the component cost estimates up to date for each control account plan.