On May 14, 2004, a dump truck transporting mixing tank T-12 from the New Hydrofracture Facility D&D Project arrived at the EMWMF.
Office of Environment, Health, Safety & Security
August 17, 2004August 17, 2004
On Friday, May 14, 2004, at approximately 11:30 a.m., a dump truck transporting mixing tank T-12 (Tank T-12) from the New Hydrofracture Facility (NHF) Decontamination and Decommissioning (D&D) Project arrived at the Environmental Management Waste Management Facility (EMWMF). Upon arrival, an incoming radiological survey was performed.