Issued to Fluor Daniel Hanford, Inc., relating to events at the Spent Nuclear Fuels Project, K-Basins and other Project Hanford Management Contract facilities at the Hanford Site
Office of Enterprise Assessments
May 26, 1999May 26, 1999
Issued to Fluor Daniel Hanford, Inc., relating to events at the Spent Nuclear Fuels Project, K-Basins and other Project Hanford Management Contract facilities at the Hanford Site
On May 26, 1999, the U.S. Department of Energy issued a Preliminary Notice of Violation and a Compliance Order (EA-1999-04) to Fluor Daniel Hanford, Inc. for violations of 10 C.F.R. Parts 820 and 830 relating to work process, design, procurement, and quality improvement deficiencies in the Spent Nuclear Fuels Project, K-Basins, and other Project Hanford Management Contract (PHMC) facilities. The deficiencies involved repetitive failures to adhere to established operational controls at nuclear facilities under the PHMC.