Independent Assessment of Specific Administrative Controls at the Savannah River Site H-Canyon - May 2023

Independent Assessment of Specific Administrative Controls at the Savannah River Site H-Canyon

Office of Enterprise Assessments

May 11, 2023
minute read time

May 2023,

Independent Assessment of Specific Administrative Controls at the Savannah River Site H-Canyon

The U.S. Department of Energy (DOE) Office of Enterprise Assessments (EA) conducted an independent assessment of the identification, development, and implementation of specific administrative controls (SACs) at the Savannah River Site H-Canyon and Outside Facilities H-Area from December 2022 to March 2023. This assessment was performed within the broader context of ongoing assessments of the development and implementation of SACs across the DOE complex. The assessment focused on the approach to meeting SAC requirements in DOE-STD-3009-94, Change Notice 3, Preparation Guide for U.S. Department of Energy Nonreactor Nuclear Facility Documented Safety Analyses.