Enterprise Assessments Review of Mine Safety, Stabilization, and Habitability at the Waste Isolation Pilot Plant – October 2015

Review of Mine Safety, Stabilization, and Habitability at the Waste Isolation Pilot Plant

Office of Enterprise Assessments

October 29, 2015
minute read time

October 2015

Review of Mine Safety, Stabilization, and Habitability at the Waste Isolation Pilot Plant

The U.S. Department of Energy Office of Enterprise Assessments (EA) conducted an independent review of a number of aspects of mine safety, stabilization, and habitability at the Waste Isolation Pilot Plant (WIPP).  EA also concurrently conducted a follow-up review of the WIPP Recovery Plan for Operating Diesel Equipment with Available Underground Airflows.  EA performed the onsite portion of its review during November 18-20, 2014, and January 6-8, March 10-13, and June 9-12, 2015.