Review of the Hanford Site Waste Treatment and Immobilization Plant Construction Quality

Office of Enterprise Assessments

January 30, 2015
minute read time

January, 2015

Review of the Hanford Site Waste Treatment and Immobilization Plant Construction Quality

The U.S. Department of Energy Office of Enterprise Assessments (EA) conducted an assessment of construction quality at the Hanford Site Waste Treatment and Immobilization Plant (WTP) during September 8-12, 2014. This EA assessment was performed in the broader context of an ongoing program of quarterly assessments of construction quality at the WTP construction site.