WVDP crews resumed waste disposal shipments in late July as part of cleanup efforts after the site moved into the 2nd phase of its operations plan.
Office of Environmental Management
August 4, 2020![Trucks carrying waste containers leave the West Valley Demonstration Project in late July en route to an offsite disposal facility. Pictured in the background is the Main Plant Process Building, which is set for demolition this year.](/sites/default/files/styles/full_article_width/public/2020/08/f77/DSCN5887_700%20pixels.jpg?itok=iiwfN_IQ)
WEST VALLEY, N.Y. – EM West Valley Demonstration Project (WVDP) crews resumed waste disposal shipments in late July as part of cleanup efforts after the site moved into the second phase of its operations plan in response to COVID-19.
The waste being shipped is from the demolition of a former utility building that began in July. The 6,955-square-foot building is an ancillary structure to the Main Plant Process Building, the last remaining major facility at the West Valley site. Teardown of the Main Plant is among EM’s 2020 priorities.
Waste disposition is the final step in the completion of deactivation and decommissioning (D&D) of onsite structures. WVDP stopped shipments in March after D&D activities were put on hold due to COVID-19.
WVDP’s second phase of its operations plan in response to COVID-19 adds high-priority operations and activities to those authorized in the first phase. The additional activities in the second phase call for use of more personal protective equipment and other health and safety precautions while workers continue to follow social distancing guidelines and other controls.
“The protection of our workers, the public, and the environment remains our priority as we resume operations at the site,” EM WVDP Director Bryan Bower said. “The resumption of waste shipments is another accomplishment the WVDP team can be proud of as we safely and compliantly continue with our resumption-of-work plan.”
Debris generated from the demolition of the former utility building is expected to fill about 75 waste containers. The waste is being sent to an out-of-state disposal facility.
“Our team members continue to use their combined knowledge to safely resume work during this challenging time,” said John Rendall, president of WVDP cleanup contractor CH2M HILL BWXT West Valley. “I’m proud of their efforts and accomplishments, and the work they continue to do on this project.”