Targeted Review of Work Planning and Control at the Hanford Central Plateau Environmental Remediation Projects
Office of Enterprise Assessments
June 22, 2015June 2015
Targeted Review of Work Planning and Control at the Hanford Central Plateau Environmental Remediation Projects
The Office of Worker Safety and Health Assessments, within the U.S. Department of Energy’s independent Office of Enterprise Assessments (EA), Office of Environment, Safety and Health Assessments, conducted a targeted review of the activity-level work planning and control processes and activities within CH2M HILL Plateau Remediation Company (CHPRC). CHPRC is the prime contractor for the environmental cleanup of the Central Plateau at the Hanford Site. The Richland Operations Office provides Federal oversight of CHPRC. The onsite portions of this EA targeted assessment were conducted from December 1-5 and December 15-19, 2014.